Currently at The Morrison we have come out of Avenida Caballeros and Alejo with new water service and are now laying water pipe in the ground onsite. The storm drain system is nearing completion and work is isolated in the SE corner of the property. The “dry utilities” which include the main electricity, telephone, cable, and gas lines have begun.

This means more trenches, so for visitors use extreme caution when onsite. The models themselves are coming right along. The framing is complete, Rough electrical, plumbing and HVAC are all nearing completion as well.

We are schedule to start production 4/25. Stop back soon to get more information about the progress we are making at The Morrison.