The Morrison Palm Springs Update: August 8, 2011

With plans to debut our model home over Labor Day weekend, our construction efforts are in full swing!

Some of the homes now have cabinetry, countertops, tile and carpet installed.  In addition, burnished block walls and corrugated metal panels that compliment the homes and define property lines are now in the process of being installed.The Morrison Palm Springs August Construction

This week, the beautiful meandering sidewalks that will surround The Morrison will begin to take shape. Within the site, the concrete streets are complete, along with several driveways and the attractive pavers used at the intersections.

All of the released homes are now framed and roofed.  With rough electrical, plumbing and HVAC complete, many now also have insulation, drywall and stucco as well.

The Morrison Palm Springs Exterior Updates

Please stay tuned for additional updates in the near future. In the meantime, if  you have any questions, please feel free to contact us! We’d love to hear from you.